56kcloud/lamasar #120

Tracking: OPC UA connector for Hall B presses

OuvertTicket de suivi

Georges Roduit a ouvert ce ticket le oct. 13, 2026 · 9 commentaires

GR
Georges Roduita ouvert ce ticket· oct. 13, 2026 - 13:14

Hall B runs twelve Engel presses with CC300 controls that expose an OPC UA server. Today their cycle data reaches Lamasar through a nightly CSV export, so the dashboards are a day behind.

This issue tracks the native connector: browse and subscribe to the press node tree, map tags to the machine model, survive network drops, and report its own health.

At risk: the certificate trust store took longer than planned and local buffering has not started.

Activité

GR
Georges Roduita ajouté
trackingconnector
oct. 13, 2026 - 13:15
GR
Georges Roduita assigné Georges Roduitoct. 15, 2026 - 05:48
GR
Georges Roduita commenté· oct. 15, 2026 - 07:56

Discussed with the Hall B team: they are fine with this approach.

GR
Georges Roduita commenté· oct. 18, 2026 - 21:19

Blocked on access to the staging plant network, asked IT.

JM
Jérémie Métraillera commenté· oct. 22, 2026 - 10:43

Unblocked, the firewall rule is in place.

GR
Georges Roduita déplacé ceci de Backlog vers Prêtoct. 24, 2026 - 19:38
GR
Georges Roduita commenté· oct. 26, 2026 - 00:06

Added tests for the edge cases mentioned above.

NV
Nicolas Varonea commenté· oct. 29, 2026 - 13:29

Looks good to me, one comment on naming.

HR
Helder Ribeiroa commenté· nov. 2, 2026 - 02:53

Moving this to the next iteration, the connector work comes first.

GR
Georges Roduita déplacé ceci de Prêt vers En coursnov. 5, 2026 - 02:02
SV
Samuel Vuadensa commenté· nov. 5, 2026 - 16:16

Demoed in the weekly, the plant manager liked it.

SP
Sandro Pereiraa commenté· nov. 9, 2026 - 05:40

Picked this up, starting with the happy path.

GR
Georges Roduita commenté· nov. 12, 2026 - 19:03

Tried it against the simulator, works for the first three presses.

Responsables

GR
Georges Roduit

Étiquettes

trackingconnector

Projet

Statut

En cours

Priorité

P0

Taille

XL · 8 pts

Itération

Iteration 21

Jalon

v0.19

Suivi

À risque

Échéance 4 déc.